Project management is not just about planning tasks and deadlines, but primarily about controlling progress and budget. One of the most effective tools for this purpose is Earned Value Management (EVM) – a method that combines data concerning scope, cost, and time, allowing for an assessment of the actual condition of the project.
Link to the calculator: EVM
EVM is a technique for measuring project progress in a quantitative and objective manner. It allows for the assessment of project performance in the context of:
what was planned,
what has been accomplished,
how much has been spent.
Here are the most important concepts and formulas used in EVM:
Definition:
The total budget of the project (the planned cost at project completion).
Formula:
PV = % of planned time × BAC
Description:
Planned value – how much work should have been completed at a given stage of the project according to the plan.
Formula:
EV = % of completed work × BAC
Description:
Earned value – the value of work actually completed to date.
Formula:
AC = Actual costs incurred
Description:
Actual cost – the total expenses incurred for the completion of the tasks performed.
Formula:
CV = EV - AC
Description:
Cost variance – the difference between earned value and actual cost.
CV > 0 – savings
CV < 0 – budget overruns
Formula:
CPI = EV / AC
Description:
Cost performance index – how much value has been obtained from each dollar spent.
CPI > 1 – project is being executed efficiently
CPI < 1 – costs are too high
Formula:
SV = EV - PV
Description:
Schedule variance – the difference between the completed and planned work.
SV > 0 – ahead of schedule
SV < 0 – delay
Formula:
SPI = EV / PV
Description:
Schedule performance index – the rate of project execution compared to the plan.
SPI > 1 – project is being executed faster than planned
SPI < 1 – project is delayed
Formula:
EAC = BAC / CPI
Description:
Estimated total cost of project completion at the current level of performance.
Formula:
ETC = EAC - AC
Description:
Estimated cost to complete the remaining work on the project.
Formula:
VAC = BAC - EAC
Description:
Variance at completion – the difference between the budget and the projected cost.
VAC > 0 – potential savings
VAC < 0 – risk of budget overruns
Formula:
TCPI = (BAC - EV) / (BAC - AC)
Description:
Performance index required to complete the project within budget.
TCPI > 1 – better performance is needed
TCPI < 1 – lower performance is sufficient to meet the goal
With EVM you can:
detect budget and time risks early,
make better decisions based on real data,
forecast the final cost and time of project completion.
Earned Value Management is not just a control tool – it is a warning system that allows projects to be managed more consciously and professionally. It is worth implementing even in smaller projects to maintain full control over costs and progress.
mateusz.florczak.96@gmail.com
+48 664-490-214
Website created in a white label responsive website builder WebWave.